Point to remember for CISA Exam:
(1)In any given scenario, when objective is to estimate project duration or timeless, answer should be PERT or CPM. However first preference to be given to PERT.
(2)In any given scenario, when objective is to monitor the project or track any milestone, answer should be Gantt Chart.
(3) In any given scenario, when objective is to consider earned value by calculating any of the following, answer should be Earned Value Analysis (EVA).
-Budget to date
-Actual spending to date
-Estimate to complete
-Estimate at completion
(4) In any given scenario, when objective is to estimate software size, answer should be FPA or SLOC. However first preference to be given to FPA.
(5) In any given scenario, when objective is to prevent project cost overruns and delays from scheduled delivery, answer should be Timebox Management.
Read more from Hemang Doshi
CISA EXAM-Testing Concept-Knowledge of Compliance & Substantive Testing Aspects Rating: 3 out of 5 stars3/5CISA Exam - Testing Concept-Fire Suppression Systems (Domain-5) Rating: 5 out of 5 stars5/5CISA Exam-Testing Concept-Backup Schemes (Full/Differential/Incremental) (Domain-4) Rating: 5 out of 5 stars5/5CISA Exam-Testing Concept-Knowledge of Logical Access Control Rating: 3 out of 5 stars3/5CISA Exam-Testing Concept-Knowledge of Risk Assessment Rating: 3 out of 5 stars3/5CISA Exam-Testing Concept-Classification of Information Assets (Domain-5) Rating: 3 out of 5 stars3/5CISA EXAM-Testing Concept-Firewall Rating: 3 out of 5 stars3/5CISA EXAM-Testing Concept-Digital Signature Rating: 3 out of 5 stars3/5CISA EXAM-Testing Concept-Roles of various functions Rating: 2 out of 5 stars2/5CISA Exam-Testing Concept-OSI Architecture (Domain-5) Rating: 0 out of 5 stars0 ratingsCISA Exam-Testing Concept-Testing in SDLC (Domain-3) Rating: 0 out of 5 stars0 ratingsCISA Exam-Testing Concept-Elements of PKI i.e CA/RA/CRL/CPS (Domain-5) Rating: 4 out of 5 stars4/5CISA Exam - Testing Concept-Network Physical Media (Fiber Optic/ UTP/STP/Co-axial) (Domain-4) Rating: 0 out of 5 stars0 ratingsCISA Exam-Testing Concept-Decision Support System (DSS) (Domain-3) Rating: 0 out of 5 stars0 ratingsCISA EXAM-Testing Concept-Recovery Time Objective (RTO) & Recovery Point Objective (RPO) Rating: 1 out of 5 stars1/5CISA Exam-Intrusion Detection System (IDS) & Intrusion Prevention System (IPS)-Domain 5 Rating: 0 out of 5 stars0 ratingsCISA Exam-Testing Concept-Biometrics (Domain-5) Rating: 0 out of 5 stars0 ratingsCRISC Exam - Study Guide Rating: 0 out of 5 stars0 ratingsCISA EXAM-Testing Concept-Check Digit,Parity Bit & Atomicity Rating: 3 out of 5 stars3/5CISA Exam-Testing Concept-Asymmetric Encryption (Domain-5) Rating: 0 out of 5 stars0 ratingsCISA-Testing Concept-Single Sign On (SSO) (Domain-5) Rating: 0 out of 5 stars0 ratings
Related to CISA Exam-Testing Concept-PERT/CPM/Gantt Chart/FPA/EVA/Timebox (Chapter-3)
Related ebooks
CISA EXAM-Testing Concept-Roles of various functions Rating: 2 out of 5 stars2/5PMI-RMP Question Bank Rating: 3 out of 5 stars3/5CISA-Testing Concept-Single Sign On (SSO) (Domain-5) Rating: 0 out of 5 stars0 ratingsCISA Exam-Testing Concept-Decision Support System (DSS) (Domain-3) Rating: 0 out of 5 stars0 ratingsCISA EXAM-Testing Concept-Recovery Time Objective (RTO) & Recovery Point Objective (RPO) Rating: 1 out of 5 stars1/5CISA Exam-Testing Concept-Asymmetric Encryption (Domain-5) Rating: 0 out of 5 stars0 ratingsCISA Exam-Testing Concept-OSI Architecture (Domain-5) Rating: 0 out of 5 stars0 ratingsCISA Exam - Testing Concept-Network Physical Media (Fiber Optic/ UTP/STP/Co-axial) (Domain-4) Rating: 0 out of 5 stars0 ratingsCISA Exam-Testing Concept-Classification of Information Assets (Domain-5) Rating: 3 out of 5 stars3/5CISA EXAM-Testing Concept-Digital Signature Rating: 3 out of 5 stars3/5CISA EXAM-Testing Concept-Check Digit,Parity Bit & Atomicity Rating: 3 out of 5 stars3/5CISA Exam-Intrusion Detection System (IDS) & Intrusion Prevention System (IPS)-Domain 5 Rating: 0 out of 5 stars0 ratingsCISA Exam-Testing Concept-Testing in SDLC (Domain-3) Rating: 0 out of 5 stars0 ratingsCISA Exam-Testing Concept-Biometrics (Domain-5) Rating: 0 out of 5 stars0 ratingsCISA EXAM-Testing Concept-Firewall Rating: 3 out of 5 stars3/5CISA Exam-Testing Concept-Elements of PKI i.e CA/RA/CRL/CPS (Domain-5) Rating: 4 out of 5 stars4/5IS Auditor - Process of Auditing: Information Systems Auditor, #1 Rating: 0 out of 5 stars0 ratingsCISA A Clear and Concise Reference Rating: 0 out of 5 stars0 ratingsCISA A Complete Guide - 2021 Edition Rating: 0 out of 5 stars0 ratingsPCI DSS 3.1: The Standard That Killed SSL Rating: 0 out of 5 stars0 ratingsCISA A Complete Guide - 2020 Edition Rating: 0 out of 5 stars0 ratingsCertified Internal Auditors A Complete Guide - 2020 Edition Rating: 0 out of 5 stars0 ratingsRisk Management Key Notes Rating: 0 out of 5 stars0 ratingsKey Risk Indicators A Complete Guide - 2020 Edition Rating: 0 out of 5 stars0 ratingsIT Audit A Complete Guide - 2019 Edition Rating: 0 out of 5 stars0 ratingsThe CISA Prep Guide: Mastering the Certified Information Systems Auditor Exam Rating: 0 out of 5 stars0 ratingsInformation technology audit The Ultimate Step-By-Step Guide Rating: 0 out of 5 stars0 ratingsGRC Standard Requirements Rating: 0 out of 5 stars0 ratingsQualified Security Assessor Complete Self-Assessment Guide Rating: 0 out of 5 stars0 ratingsCRISC A Complete Guide - 2019 Edition Rating: 0 out of 5 stars0 ratings
Professional & Vocational Exams For You
PTCE: Pharmacy Technician Certification Exam Premium: 4 Practice Tests + Comprehensive Review + Online Practice Rating: 0 out of 5 stars0 ratingsAdult CCRN Exam Flashcards, Second Edition: Up-to-Date Review and Practice Rating: 5 out of 5 stars5/5Criminal Law Rating: 0 out of 5 stars0 ratingsMedical Terminology Rating: 5 out of 5 stars5/5NCLEX-RN Prep Plus: 2 Practice Tests + Proven Strategies + Online + Video Rating: 3 out of 5 stars3/52023/2024 ASVAB For Dummies (+ 7 Practice Tests, Flashcards, & Videos Online) Rating: 0 out of 5 stars0 ratingsAdult CCRN Exam Premium: For the Latest Exam Blueprint, Includes 3 Practice Tests, Comprehensive Review, and Online Study Prep Rating: 0 out of 5 stars0 ratingsMedical Assistant Exam Prep: Your All-in-One Guide to the CMA & RMA Exams Rating: 0 out of 5 stars0 ratingsASVAB For Dummies Rating: 4 out of 5 stars4/5Legal Research: a QuickStudy Laminated Law Reference Rating: 0 out of 5 stars0 ratingsPTCE - Pharmacy Technician Certification Exam Flashcard Book + Online Rating: 0 out of 5 stars0 ratingsLMSW Passing Score: Your Comprehensive Guide to the ASWB Social Work Licensing Exam Rating: 5 out of 5 stars5/5EMT (Emergency Medical Technician) Crash Course Book + Online Rating: 5 out of 5 stars5/5CALIFORNIA SUBJECT EXAMINATION FOR TEACHERS (CSET): Passbooks Study Guide Rating: 0 out of 5 stars0 ratingsTorts Mnemonics and Definitions: Mnemonics, #3 Rating: 0 out of 5 stars0 ratingsMaster the NCLEX-RN Exam Rating: 5 out of 5 stars5/5The Official Highway Code: DVSA Safe Driving for Life Series Rating: 3 out of 5 stars3/5Family Nurse Practitioner Certification Exam Premium: 4 Practice Tests + Comprehensive Review + Online Practice Rating: 0 out of 5 stars0 ratingsCPA Review Notes: BEC 2022 Rating: 3 out of 5 stars3/5LSAT Test Prep Essential Vocabulary--Exambusters Flash Cards--Workbook 1 of 3: LSAT Exam Study Guide Rating: 1 out of 5 stars1/5Master the Boards USMLE Step 3 7th Ed. Rating: 5 out of 5 stars5/5Medical Terminology:The Basics: a QuickStudy Laminated Reference Guide Rating: 0 out of 5 stars0 ratingsMaster the Massage Therapy Exams Rating: 5 out of 5 stars5/5Praxis Core 2023-2024 For Dummies Rating: 0 out of 5 stars0 ratings
Reviews for CISA Exam-Testing Concept-PERT/CPM/Gantt Chart/FPA/EVA/Timebox (Chapter-3)
3 ratings1 review
- Rating: 3 out of 5 stars3/5The chapter was well explained and the sample questions drove the point home. Thanks